SCOPE OF THE WORK
- Construction of a 25 m long pre-cast concrete box girder bridge with cast-in-situ concrete abutments
540 m of approach roadwork including:
- Clearing and grubbing
- 22,000 m3 of excavation
- Production and placement of road gravels
- Paving
- Traffic control, including detours
- Design, supply and installation of 958 m2 of MSE retaining walls, complete with manufacturing of required gravels