PROJECT DETAILS

PROJECT TYPE
Current, Municipal Projects
REGION/LOCATION
Victoria, BC
START DATE
October 2024
COMPLETION DATE
June 2026

SCOPE OF THE WORK

Underground installation of approximately:

  • 1,354m of Water main, complete with 40 valves, 95 fittings,13 tie in’s to existing mains , and multiple services connections.
  • 885m of Sanitary gravity main including 12 manholes, and multiple services connections.
  • 485m of Sanitary forcemain including a new pump station.
  • 950m of Storm drain including 30 manholes, 18 Catch Basin’s, multiple connections to existing large box culverts, and multiple services connections.
  • More than 27,000 square meters of of asphalt paving.
  • More than 2,000 meters of new curbs
  • More than 3,000 square metes of new sidewalk
  • Intersection, bike lane and public transit upgrades.
  • Site beautification, including new trees, irrigation, fencing, and site furnishings.
`