PROJECT DETAILS

PROJECT TYPE
Heavy Civil Projects
REGION/LOCATION
Port Alberni, BC
START DATE
August 2011
COMPLETION DATE
September 2011

SCOPE OF THE WORK

  • Construction of an 18m long by 7.2m wide Precast Concrete Girder Bridge
  • Supply and installation of pre-cast concrete abutment cap beams, precast girders (6), precast parapets, parapet railings and concrete roadside barriers
  • Supply and Installation of 72 LM of 406 diameter steel pipe piles
  • Construction of roadway approaches
  • Traffic management including detours
  • Demolition and removal of existing structure (culvert)
  • Supply and installation of new sanitary force main suspended from bridge
  • Supply and placement of road gravels c/w asphalt paving
  • Environmental Management and Quality Management
`