PROJECT DETAILS

PROJECT TYPE
Municipal Projects
REGION/LOCATION
Nanaimo, BC
START DATE
September 2018
COMPLETION DATE
June 2019

SCOPE OF THE WORK

The works consist of the installation of 700lm of PVC (size 200mm, 300mm) watermains, 31x water service connections, 4x fire hydrants, 280lm of sanitary (200mm & 450mm) with 10x sani services, and storm drains, curbs (285ms concrete, 30ms asphalt) and sidewalks (460lm), asphaltic concrete paving (240te trailway, 310te roadway, 40te driveway), pedestrian bridge and electrical scope of work.

`