SCOPE OF THE WORK
The works consist of the installation of 700lm of PVC (size 200mm, 300mm) watermains, 31x water service connections, 4x fire hydrants, 280lm of sanitary (200mm & 450mm) with 10x sani services, and storm drains, curbs (285ms concrete, 30ms asphalt) and sidewalks (460lm), asphaltic concrete paving (240te trailway, 310te roadway, 40te driveway), pedestrian bridge and electrical scope of work.