PROJECT DETAILS

PROJECT TYPE
Municipal Projects
REGION/LOCATION
Nanaimo, BC
START DATE
February 2018
COMPLETION DATE
December 2018

SCOPE OF THE WORK

The Northfield/Boundary/19a Project consists of the widening of Highway 19A for the installation of an acceleration/merge lane, widening of Northfield Road for the addition of a left turn bay, extension of corrugated steel pipe pedestrian tunnel, removal and installation of concrete retaining walls for pedestrian ramps, modification of a signalized intersection, addition of a signalized intersection, street lighting, approximately 800m of concrete curb, 500m2 of concrete sidewalk, replacement of 100m of watermain, adjustment of sanitary sewer items, installation of 400m of storm sewer piping, and 1500 tonnes of asphalt paving and all other work incidental thereto.

`