PROJECT DETAILS

PROJECT TYPE
Hydroelectric Projects
REGION/LOCATION
Tahsis, BC
START DATE
May 2011
COMPLETION DATE
November 2011

SCOPE OF THE WORK

  • Construction of Concrete Intake and Weir Structures
  • Forming, batching, and pouring of reinforced concrete – 393 m3
  • Supply and installation of misc. metals: platform grating, handrails, slide gates, etc.
  • Installation of Obermeyer weir
  • Multiple creek diversions for staged weir construction
  • Drilling and grouting of rock dowels
  • Erosion and sediment control
  • Supply and Installation of Penstock – 2,156 m total length
  • Supply and Installation of 54” HDPE Pipe – 688 lm
  • Supply and Installation of 48” HDPE Pipe – 277 lm
  • Supply and Installation of 44.5” Ductile Iron Pipe – 1,191 lm
  • Trench rock removal– 1,352 lm
  • Supply and Installation of a 27 m span pipe bridge
`