Barrs Mountain Reservoir Replacement Project

Barrs Mountain Reservoir Replacement Project

The Town of Tofino BC has awarded Hazelwood Construction Services Inc. with the contract for the Barrs Mountain Reservoir Replacement Project.

Award Date: 02/23/2017
Award Amount: $821,452.08 + Tax
Start Date: May 2017
Estimated Completion Date: September 2017
Project Engineer: McElhanney Consulting

The work involves the supply and installation of a 1124m3 bolted steel reservoir and foundation; removal of 120m of AC watermain; supply and install of 170m of 250mm HDPE water main and associated valves and fitting; and misc. site works and fencing.

`