Ahousaht-Anderson Ck Watermain Replacement
Ahousaht-Anderson Ck Watermain Replacement
Ahousaht First Nation has awarded Hazelwood Construction Services Inc. with a contract for the Ahousaht-Anderson Ck Watermain Replacement.
Award Date: 07/26/2018
Award Amount: $2,880,259
Start Date: 08/07/2018
Estimated Completion Date: 11/30/2018
The construction of 1,210 metres of 200mm HDPE water supply main from the Anderson Creek Dam to Matilda Inlet near Ahousaht, B.C. The work includes but is not limited to:
• 1,210 metres of water mains
• 1,126 metres of access road construction
• Rock blasting, crushing, screening
• Bridge construction